Kaizen Description

After implementing temporary jig base solution: Trial was completed on time No production delay occurred Resource utilization improved Dependency on vendor was reduced (temporarily) Quick problem-solving approach increased team efficiency

Before Situation

🔹 Before (Current Condition / Problem) During Joyar tablet trial, current test jig base was not available, as all jig bases were sent to vendor for modification. Because of this: Current testing could not be performed Trial completion was at risk Production timeline was getting delayed No immediate alternative was available

After Situation

🔹 After (Improvement / Countermeasure) A temporary solution was developed by the team: Checked compatibility with other model jig bases Identified that Sprocom tablet jig base could be used Adjusted Joyar jig with Sprocom base using glue/feviquick (temporary setup) Successfully completed current testing and trial

Kaizen Start Date

14-04-2026

Kaizen End Date

16-04-2026

Result

Productivity

Cost Calculation Sheet
Improvement Details