Before Situation

The darkness of the QR code of the charger being made on the charger line was low. After the charger reached the floor, proper scanning was not happening due to which the line was getting hampered.

After Situation

The problem occurring in charger scanning was rectified with the help of my testing team by correcting the cracks in the charger code due to which now the charger is being scanned properly on line.