Kaizen

Back

HOD ok
by : Jai Prakash Singh

KPO: ok
by : Jai Prakash Singh

CI: ok
by : Shubham Srivastava

Team Member - 1
Team Member - 2
HOD
KPO
CI Team
Finance
Kaizen Theme
Kaizen Description

POKA Yoke add on line

Before Situation

At battery cover pressing stage in all SP models some devices got bay pass from this stage and there was no any check point was available at next stage for detect the bay pass issue on line.

After Situation

Now we have add scanning system in battery cover pressing jig and device will be scan in IMS and it's check point has been added at next scanning stage so that there is no any check chance that bay pass can be go.

Kaizen Start Date

20-03-2025

Kaizen End Date

30-04-2025

Result

Quality

Cost Calculation Sheet
Improvement Details