Before we were facing high cycle time issue in Z35_Main in mounter machine so we were not achieving our shift production target as per model capacity.
Before CT was 44.2 sec per board.
After analysis and optimization the DGS program as per machine part placement with sequence manner.
Now cycle time is 42.8 sec per board. |