Kaizen Description

Before We are using Z Tcode in SAP PCBA moved After Physical scanning by PQC and after receiving in SMT they will accept In SAP. and this process is taking time.

Before Situation

Before We are using Z Tcode in SAP PCBA moved After Physical scanning by PQC and after receiving in SMT they will accept In SAP. and this process is taking time.

After Situation

Now we have Changed the process in which PQc is sharing Detail on requisition Slip after Physical validation mc is sharing Document number after Posting . PCBA movement is allow only after Posting.

Kaizen Start Date

06-11-2024

Kaizen End Date

07-11-2024

Result

Productivity

Cost Calculation Sheet
Improvement Details