Kaizen Theme
Kaizen Description

Earlier there was keypad failure for which we have changed the process.

Before Situation

In the first assembly, keypad failure occurred too much and we analyzed to find out that gum issue was found on the keypad or human then in smt I analyzed and found out that there was tape paste on the keypad due to which keypad failure occurred.

After Situation

Now we have started using pen marker instead of tape, which has reduced the incidence of keypad failure.

Kaizen Start Date

11-07-2024

Kaizen End Date

12-07-2024

Result

Moral