Kaizen Theme
Kaizen Description

During PM Time When conveyor set manually conveyor alignment out

Before Situation

Reflow conveyor used to be out of alignment after doing PM activity sometimes when we set the conveyor manualy.

After Situation

Then whenever we started doing the conveyor of PM reflow machine with automatic machine, there was imporvement in its alignment and we had to set the automatic conveyor in PM and changeover time. so that we do not suffer loss in production.

Kaizen Start Date

15-04-2024

Kaizen End Date

18-04-2024

Result

Productivity

Cost Calculation Sheet
Improvement Details