Third floor repair area too congested because two department are work in Small cabin. We have no space to do any other work.

Before Situation

Third floor repair area have no space. because two department work together in small office area. many time our material are miss and always data mismatch to material gap issue. but we have no space to other activity.

After Situation

we have separate office area in third floor to done batter work. When we have space in third floor repair office area. so we done our work proper. no any other are disturb us to during the work. and our material also have in save area.

Kaizen Start Date

16-03-2023

Kaizen End Date

16-03-2023

Result

Quality