Kaizen

Back

HOD ok
by :

KPO: ok
by : Barjinder kumar

CI: ok
by :

Team Member - 1
Team Member - 2
HOD
KPO
CI Team
Finance
Kaizen Theme
Kaizen Description

Process changes for speaker bracket fix process in Nokia shadow cat plus

Before Situation

Before process are first current test >>battery fix>>battery pressing>>B2B Pressing >>speaker bracket fix. in this process at current stage continuously failures are coming due to sub pcba not proper fixed.

After Situation

Now process are first speaker bracket fix>> current test >>battery fix>>battery pressing>>B2B Pressing >>in this process at current stges zero failure coming of SUB PCBA loose because sub PCBA fixed with speaker bracket.

Kaizen Start Date

31-08-2022

Kaizen End Date

31-08-2022

Result

Productivity

Cost Calculation Sheet
Improvement Details