Kaizen

Back

HOD ok
by :

KPO: ok
by : Manoj Kumar Satyawali

CI: OK
by :

Team Member - 1
Team Member - 2
HOD
KPO
CI Team
Finance
Kaizen Theme
Kaizen Description

Second Floor air shower, sometimes there was a problem in running , because there is limit switch not working properly , and after making its adjustment, it used to work properly but after some time the same problem used to come again and again

Before Situation

Second Floor air shower, sometimes there was a problem in running , because there is limit switch not working properly , and after making its adjustment, it used to work properly but after some time the same problem used to come again and again

After Situation

I have modified the circuit and disconnect door limit switch and use door magnetic switch for controlling ,after that every operation is working fine , without fail

Kaizen Start Date

03-07-2022

Kaizen End Date

03-07-2022

Result

Productivity

Cost Calculation Sheet
Improvement Details