Kaizen Star - Plant 1
Aakash Reddu
April - 2024
Total1
| Sr. No | Kaizen No | Kaizen Theme | Initiator | Team | Before Situation |
After Situation |
Month | ||
| 1 | LCIK - 36803 |
Process modification for productivity |
Adarsh giri , 51009642 |
Before process are first current test >>battery fix>>battery pressing>>B2B Pressing >>speaker bracket fix. in this process at current stage continuously failures are coming due to sub pcba not proper fixed. | Now process are first speaker bracket fix>> current test >>battery fix>>battery pressing>>B2B Pressing >>in this process at current stges zero failure coming of SUB PCBA loose because sub PCBA fixed with speaker bracket. | 08/2022 | |||
| 2 | LCIK - 37602 |
Process modification for dust reduction in Nokia shadowcat |
Pawan Kumar , 51009498 |
Gange Naresh , 51009421 Abhin Manra , 51009366 |
In before situation, We are fixing Camera sleeve in display assembly and then buckling front camera , due to this easily dust entered in front camera cavity. | In after situation, Now we are fixing camera sleeve first in front camera and after air ionizer fixed the front camera. | 12/2022 | ||
| 3 | LCIK - 36631 |
Process Modification for Defect control |
, 51008095 |
Before battery cover installation>>battery cover pressing >>Paste Camera lens>>Camera lens Pressing this stages are sequence wise in this sequence observe that is the dust particles in back cameras. | Now we changes the process is battery cover installation >>Paste Camera lens>>Camera lens Pressing>>battery cover pressing this stages are sequence wise so installation of battery cover stage are easily managed in cleaning room and after that camera lens assy done. | 08/2022 | |||