** ***** Give Kaizen on Theme - Near Miss & win exciting prizes ! *****

Kaizen Corner

Sr. No Kaizen No Kaizen Theme Initiator Team Before
Situation
After
Situation
Month
1 LCIK - 39945
Used PCBA Disposal
Krishna Kumar Singh , 51010395
, 51010363
At present there is no any defined process to consume these used PCBA on line and the leader of the line also tries to consume these PCBA but there comes issue of Not Scan, Already bind, Damaged or block PCBA, Not From SMT issue. So this takes time and the used PCBA are rarely consumed on line at the same shift and these creates used PCBA pending on floor. f we delegate a single manpower in each shift from MRN team who will be responsible to segregate and run the used PCBA. He will segregate all the used PCBA received in kit and run all the PCBA by binding the PCBA offline if not scan issue is coming, if already bind then make data and send to repair for unbind and then do software and then run on line. It will clear the used PCBA in same shift and it will lead to no any PCBA hold on floor 03/2024
2 LCIK - 39470
Used PCBA Disposal
Priyamjit Paul , 51009135
At present there is no any defined process to consume these used PCBA on line and the leader of the line also tries to consume these PCBA but there comes issue of Not Scan, Already bind, Damaged or block PCBA, Not From SMT issue. So this takes time and the used PCBA are rarely consumed on line at the same shift and these creates used PCBA pending on floor. If we delegate a single manpower in each shift from MRN team who will be responsible to segregate and run the used PCBA. He will segregate all the used PCBA received in kit and run all the PCBA by binding the PCBA offline if not scan issue is coming, if already bind then make data and send to repair for unbind and then do software and then run on line. It will clear the used PCBA in same shift and it will lead to no any PCBA hold on floor 01/2024
3 LCIK - 39604
Used PCBA Disposal
Sachin yadav , 51009625
, 40005
At present there is no any defined process to consume these used PCBA on line and the leader of the line also tries to consume these PCBA but there comes issue of Not Scan, Already bind, Damaged or block PCBA, Not From SMT issue. So this takes time and the used PCBA are rarely consumed on line at the same shift and these creates used PCBA pending on floor. If we delegate a single manpower in each shift from MRN team who will be responsible to segregate and run the used PCBA. He will segregate all the used PCBA received in kit and run all the PCBA by binding the PCBA offline if not scan issue is coming, if already bind then make data and send to repair for unbind and then do software and then run on line. It will clear the used PCBA in same shift and it will lead to no any PCBA hold on floor 02/2024
 Previous  76  77  78  79  80 Next