** ***** Give Kaizen on Theme - Near Miss & win exciting prizes ! *****

Kaizen Corner

Sr. No Kaizen No Kaizen Theme Initiator Team Before
Situation
After
Situation
Month
1 LCIK - 41654
ZM2M_BATCH_CHANGE new T code develop for Kit clearance
Dimple Kumar , 52392
Lalit Kumar Bansal , 58214
Previously, we using to manually batch check each part one by one line item in SAP. This process was time-consuming and took more than one hour to clearing the Kit posting to floor. Now we are collaborating with the SAP team to develop the ZM2M_BATCH_CHANG T-code, which will provide a batch of all parts in a single run and all Kit posting one shot 10/2024
2 LCIK - 42474
ZM2M_BATCH_CHANGE new T code develop for Kit clearance
Dimple Kumar , 52392
Lalit Kumar Bansal , 58214
Previously, we using to manually batch check each part one by one line item in SAP. This process was time-consuming and took more than one hour to clearing the Kit posting to floor. Now we are collaborating with the SAP team to develop the ZM2M_BATCH_CHANG T-code, which will provide a batch of all parts in a single run and all Kit posting one shot 05/2025
3 LCIK - 38036
Zig modification.
PANKAJ KUMAR , 51009177
Vinay Shekhar , 59429
Prakash , 51009675
Before situation the model Lava Z93P RF jigs running only for Z3UP after some time new model come we implemented same jigs into Z3UP model. If new model come of Lava Z93P (Z3 UP) we are implemented Z93P rf jigs into the Z3 Model, We removed some material from the base of rf jigs and running this jigs for both model of lava Z3 and Z93P models. and pogo pin removed from the base as per model wise. 02/2023