Kaizen Star - Plant 1
Aakash Reddu
April - 2024
Total1
| Sr. No | Kaizen No | Kaizen Theme | Initiator | Team | Before Situation |
After Situation |
Month | ||
| 1 | LCIK - 42761 |
Safety point of view |
Krishna Kumar Singh , 51010395 |
Before all wires were hanging of machine and equipment . Due to this there was more chances to accident . | I have talk to maintenance team and all wires have routed with spiral very wells . Now problem has solved . | 07/2025 | |||
| 2 | LCIK - 42764 |
Safety point of view |
Krishna Kumar Singh , 51010395 |
Before smoker pipe Cap was plastic . Due to this there was chances to incident of fire . | To talking with the maintenance team we have apply the SS cap of smoker pipe. Now problems has solved . | 07/2025 | |||
| 3 | LCIK - 42290 |
Safety point of view |
Krishna Kumar Singh , 51010395 |
Before any equipment stand near the clean room due to this many time clean room mirror had broken and spread the floor for this , there was more chances to incident . | Now we provide the proper location for all equipment so that everyone put the equipment its place and we could save to broke the mirror of clean room as well as save also anyone to incident . | 03/2025 | |||