Kaizen Star - Plant 1
Aakash Reddu
April - 2024
Total1
Sr. No | Kaizen No | Kaizen Theme | Initiator | Team | Before Situation |
After Situation |
Month | ||
1 | LCIK - 37378 |
![]() Rf jig modifie for current test |
Saroj kumar kar , 51006585 |
Mohd Farzan , 51009674 Sumant Kumar Yadav , 51009654 |
We are use rf jig only rf stage. | After modification we are use rf jig rf stage and current stage both. | 11/2022 | ||
2 | LCIK - 37600 |
![]() RF jig modification in BLAZE 5G for easiness in buckling RF connector. |
Abhin Manra , 51009366 |
Pawan Kumar , 51009498 |
In previous process RF cable buckling was done separately. Single RF cable operated with single jig causing operator consuming more time. | In present process RF cable buckling divided as both RF cables will be buckled at sub PCBA side first , then at main PCBA side. | 11/2022 | ||
3 | LCIK - 42079 |
rf flag detection |
Pawan Kumar Yadav , 51010085 |
Vishal , 51009466 |
before we have faced 5% rejection rf calibration flag down issue in yuva2_5g , which have no detection in teh smt at any stage | Now at rf stage the after every GSM ,LTE,NR test the tool will validate the flag status .after that no rejection found in assembly | 01/2025 | ||